if p men take q hours to dig 3*3*4 well. Then how many days ‘r’ men will take to dig 8*3*5 well.
if p men take q hours to dig 3*3*4 well. Then how many days ‘r’ men will take to dig 8*3*5 well.
Anwer: 10pq/3r hours Solution: 3*3*4 well is work done in p*q man hours 8*3*5 well is work done in pq(8*3*5)/(3*3*4) = 10pq/3 man hours now work = 10pq/3 = r*x manhousrs x = 10pq/3r hours
New Question: Unit Digits and Last Two Digits
In a test match in cricket, the scores of Rohit and Vir...
By nhuadovan , 11 months ago
New Question: Unit Digits and Last Two Digits
The 111th digit of the series 149162536496481........ i...
By nhuadovan , 11 months ago
New Question: Unit Digits and Last Two Digits
how many perfect squares of natural numbers between 300...
By nhuadovan , 11 months ago
New Question: Permutation and combination
Find the number of ways to distribute 2n different ball...
By nhuadovan , 11 months ago
A cube is divided into two parts by a plane passing thr...
By nhuadovan , 11 months ago
RE: List of Authors to be read
Thank you for sharing the list ... i will try to read o...
By Anonymous , 1 year ago
New Question: Permutation and combination
The collection of the questions are really great it wil...
By Anonymous , 2 years ago
Mark bought 45 grinders for Rs. 2215, while carrying h...
By Anonymous , 2 years ago
New Question: Unit Digits and Last Two Digits
Great thread ,i tried to do these but not able to do..t...
By Anonymous , 2 years ago
0 comments